How to Calculate Predetermined Manufacturing Overhead Rate

Ever felt lost figuring out how much your products really cost to make? You’re not alone—understanding how to calculate the predetermined manufacturing overhead rate is essential for accurate budgeting and smart pricing.

Getting this calculation right helps you avoid nasty surprises, set competitive prices, and keep your business running smoothly. In this article, you’ll find a clear, step-by-step guide to calculating the rate, practical tips to get it right, and insights to help you make more informed business decisions.

Related Video

How to Calculate the Predetermined Manufacturing Overhead Rate

Understanding and calculating your predetermined manufacturing overhead rate is an essential skill for anyone involved in business budgeting, cost accounting, or managerial decision-making. It’s a core concept in manufacturing, helping you estimate production costs, set prices, and plan production schedules effectively.

Let’s break down what the predetermined overhead rate is, why it matters, how to calculate it step-by-step, and what you need to keep in mind to use it successfully.


What Is the Predetermined Manufacturing Overhead Rate?

The predetermined manufacturing overhead rate is a calculation that helps you estimate the indirect manufacturing costs—such as factory rent, equipment maintenance, or supervisor salaries—assigned to each unit of product.


How to Calculate Predetermined Overhead Rate: Formula & Uses - calculate predetermined manufacturing overhead rate

Unlike direct costs (like raw materials and direct labor), these overhead costs can’t be traced directly to a product, so the predetermined rate spreads them fairly across all finished goods.

Think of it as a forecast or an average: you calculate this rate at the beginning of a period (like a fiscal year or quarter) and use it to apply overhead costs to production jobs as work progresses.


The Predetermined Overhead Rate Formula

Here’s the simple, universal formula:

Predetermined Manufacturing Overhead Rate
= Estimated Total Manufacturing Overhead Costs
÷ Estimated Total Amount of Allocation Base

Let’s define those terms in everyday language:

  • Estimated Total Manufacturing Overhead Costs:
    This is your best prediction of all indirect costs for the period—things like utilities, depreciation, machinery repairs, and indirect labor.

  • Estimated Total Amount of Allocation Base:
    This is a measure you’ll use to “spread” overhead costs. Common allocation bases include:

  • Direct labor hours
  • Direct labor cost
  • Machine hours
  • Units produced


How to Calculate Predetermined Overhead Rate: Formula & Uses - wikiHow - calculate predetermined manufacturing overhead rate

Pick the base that makes the most sense given your type of manufacturing.


Why Use a Predetermined Overhead Rate?

You might be asking, why not just use the actual overhead costs at the end of the period? Here’s why the predetermined rate is so valuable:

  • Timely Costing:
    You need cost information in real-time—while work is ongoing—not months later when the period ends.
  • Better Planning and Pricing:
    Accurate, upfront estimates help you set realistic selling prices and production quotas.
  • Consistent Application:
    Prevents wild cost swings from month-to-month fluctuations in expenses or production volumes.

Step-by-Step: How to Calculate the Predetermined Overhead Rate

Ready to calculate? Follow these straightforward steps:

1. Estimate Total Manufacturing Overhead

List all your indirect manufacturing expenses for the coming period. This includes:

  • Factory rent, property taxes, and insurance
  • Machine maintenance and depreciation
  • Utilities (electricity, water for production)
  • Indirect materials (lubricant, cleaning supplies)
  • Indirect labor (supervisors, janitors)

Practical Tip:
Look at past months’ expenses, adjust for known changes (like equipment upgrades), and build in seasonal fluctuations.


Predetermined Overhead Rate Formula | Calculator (with Excel ... - EDUCBA - calculate predetermined manufacturing overhead rate

2. Choose Your Allocation Base

Decide which base most closely aligns with how overhead costs move. For example:

  • If your factory is labor-intensive, direct labor hours or costs may fit best.
  • If machines drive your process, machine hours could be more accurate.

Keep this base consistent for reliable results.

3. Estimate the Total Amount of Your Allocation Base

Predict the total number of direct labor hours, machine hours, or total units you plan to use or produce in the upcoming period.

Advice:
Be realistic but ambitious! Overestimating or underestimating will skew your overhead applied and may affect profits or decision-making.

4. Calculate the Rate

Plug your numbers into the formula:


Predetermined Overhead Rate Calculator - Calculator Academy - calculate predetermined manufacturing overhead rate

Predetermined Overhead Rate
= (Estimated Total Manufacturing Overhead Costs)
÷ (Estimated Total Allocation Base)

Example Calculation:

Suppose, for the year, you estimate:


Predetermined Overhead Rate Formula | How to Calculate? - WallStreetMojo - calculate predetermined manufacturing overhead rate

  • Total manufacturing overhead costs: $120,000
  • Total machine hours (your chosen base): 20,000 hours

Predetermined Overhead Rate = $120,000 / 20,000 machine hours = $6.00 per machine hour

So for every machine hour worked, you’ll assign $6 of overhead to jobs in progress.

5. Apply the Rate During Production

As you track actual production, you’ll use this rate to assign overhead:

  • If a job takes 100 machine hours, overhead applied = 100 x $6 = $600.
  • Do this for each job or production batch until the period ends.

Benefits of Using the Predetermined Overhead Rate

Utilizing this rate offers numerous advantages:


Predetermined overhead rate - Accounting For Management - calculate predetermined manufacturing overhead rate

  • Enables prompt decision-making by providing instant cost data.
  • Improves product costing accuracy—costs are more evenly allocated.
  • Facilitates budgeting and variance analysis, letting you compare expected and actual costs for better control.
  • Helps with pricing strategies, ensuring indirect costs are covered when quoting sales orders.

Common Challenges and How to Overcome Them

Every system has its pitfalls. Be aware of these common issues:

  • Estimation Errors:
    If budgeted figures are way off, the overhead applied will be inaccurate.
  • Solution: Use at least three years of historical data, and revisit estimates regularly.

  • Choice of Allocation Base:
    Picking the wrong base can lead to unfair or distorted overhead assignment.

  • Solution: Analyze which base actually correlates with your overhead patterns. Review annually.

  • Changes in Production Mix:
    If your operations change drastically mid-period, your rate may no longer fit.

  • Solution: Consider recalculating the rate if a significant shift happens.

  • Over- or Under-Applied Overhead:
    Actual overhead rarely matches applied overhead exactly.

  • Solution: At period end, reconcile the difference (often by adjusting cost of goods sold).


How To Calculate Predetermined Overhead Rate (With Examples) - calculate predetermined manufacturing overhead rate

Best Practices and Tips

Here’s how to maximize the usefulness of your predetermined overhead rate:

  • Review and Update Annually:
    Adjust your overhead rate before each accounting period to reflect changing costs or production methods.

  • Involve Multiple Departments:
    Get input from finance, production, and engineering when estimating cost drivers and overhead.

  • Document Assumptions:
    Keep records of how you arrived at your estimates and chosen allocation base.

  • Use the Rate for Variance Analysis:
    Compare the applied overhead (using the rate) to actual overhead and explore major differences. It’s a valuable management control tool.

  • Educate Teams:
    Make sure supervisors and cost accountants know how and why the rate is used so there’s buy-in and understanding.


Practical Example


Predetermined Overhead Rate (POHR): Formula and Calculation - calculate predetermined manufacturing overhead rate

Let’s bring it all together with a quick scenario.

ABC Widget Factory estimates for next year:

  • Total manufacturing overhead: $300,000
  • Chosen allocation base: direct labor hours
  • Estimated total direct labor hours: 60,000

Calculation:

Predetermined Overhead Rate = $300,000 ÷ 60,000 = $5.00 per direct labor hour

If Job #47 requires 250 direct labor hours:

  • Overhead applied = 250 x $5 = $1,250

Assign this $1,250 to Job #47 as its share of overhead.


Frequently Asked Questions (FAQs)

What is the difference between actual and predetermined overhead rates?

Predetermined overhead rates are calculated before the accounting period starts, using budgeted numbers, to help apply costs in real time. Actual overhead rates use real expenses and activity levels, but are only available after the period ends. The predetermined rate allows for timely costing and operational decisions.


How do I decide which allocation base to use?

Choose the base (like direct labor hours, machine hours, or units produced) that best reflects how your overhead costs increase or decrease. Analyze your process: if machines are your major cost, use machine hours; if it’s mostly labor, use direct labor hours or cost.


What happens if my estimates are inaccurate?

If your estimated costs or bases are off, you may apply too much or too little overhead. At period end, compare the total applied overhead to the actual overhead incurred. Adjust the difference by either charging it to cost of goods sold or prorating it among jobs.


Can I change the predetermined overhead rate during the year?

Normally, you set it at the start of the period and stick with it. However, if there’s a major, unforeseen change (like a new factory opening or a large change in production), management may decide to recalculate and apply a new rate.


Why not just use actual overhead rates instead of predetermined rates?

Using the actual rate means you must wait for all cost data at period end, delaying important business decisions. The predetermined rate provides timely, consistent information that’s critical for competitive pricing, job costing, and budget monitoring throughout production.


In Summary

The predetermined manufacturing overhead rate is a straightforward yet powerful tool for cost allocation in manufacturing. By carefully estimating your overhead costs and allocation base, and applying the rate consistently, you can gain sharper insights into your production costs, improve pricing decisions, and ensure financial control over your operations.

Staying diligent with your estimates, reviewing regularly, and involving all relevant departments will ensure your predetermined overhead rate works to your company’s advantage—giving you the clarity and control you need to thrive in a competitive market.